West Hartley Drive Extension from North Main to Westover
Week of 5/14/2012
RAIN!!!!
We will try and get started on the sewer line relocation at 53:85 station tomorrow morning. This morning we will inspect the erosion control to make sure it is working properly, make sure all road signs are up and try to start again Tuesday morning. The sewer line relocation is the most important item for this week. I am posting some photos of last week;
This is storm 30" RCP pipe at station 45:50

This is a Temporary Stream Crossing at station 53:85

Week of 5/7/2012
This week we will have started drilling the bridge Bent 2 piers.
Erosion Control measures will continue on to Basin # 11A.
When we have Basins's 9,10,11A complete we will then start the sewer and storm pipe construction.
On Hartley and Main we have started the storm water construction and also will start the curb and gutter this week and if weather permitting we will place asphalt base.




Week of 4/30/2012
This week the cranes will have been assembled and work on the bridge will begin. They will start by drilling for piers on the Bents of the bridge.
Erosion control measures are still in progress so basins 9,10,11A will be constructed near the 60 " concrete pipe area and creek crossing.
Construction on the Main Street & W. Hartley Dr. will continue with storm pipe and grading.



Week of 4-16-2012
This week we will start work on West Hartley Dr. at the cul-de-sac. Temporary slope drains will be installed from structure 18 and storm pipes and catch basins we be installed headed in easterly direction.
On Ingleside Dr. we will have installed more erosion control and a construction entrance. We will ease into phase 2 of the project and continue in a westerly direction with clearing and grubbing.


The drilling for piers on walls continues on as well


HEADING WEST
On to the 60 "



Week of 4/9/2012
This week we will move to the second sound wall and start drilling and setting piles for this one.
Erosion control measure are continuing;
Basin #1 is almost complete.
Basin 8A has had the trees cleared and will be started this week.
We may also start the clearing phase 2 headed west of Ingleside once this basin is constructed.
Progress pictures;

The End Bents fill sections on both sides for the bridge have been built up. Drilling rig and crane are at second wall location this morning at the top right hand side of this hill in above picture.

This photo is the permanent Basin #1 almost complete.
Week of 4/2/2012
More Erosion Control, Surveying, and Hauling of Unclassified Soils.
Drilling Holes and Placement of Piles for Sound Barrier Wall at Ingleside Street location.
Week of 3/26/2012
Construction of Basin # 1 will take place this week and into next week.
Hauling out of soil and rough grading of road will take place.
A Terex Crane will come in on Ingleside Rd for the constructing of noise barrier wall.


Erosion Control measure will be constructed through out project and maintained.


Week of 3/19/2012
This week we will have dump trucks hauling from both locations;
West Hartley Dr. and Ingleside Dr.
Some clearing of trees will take place on Westover.
More erosion control measures will be put in place as well as seeding and mulching.
* Heavy Equipment will be on roadways coming to and leaving work site.*
Week of 3/12/2012
Armoring of the Creek Bank
Erosion Control
Clearing and Grubbing
These items will be addressed this week. Heavy equipment will be entering and exiting job site from 8 am to 4 PM daily.
There will be a meeting with NCDWQ on Wednesday at 2 PM near station 53+85 to discuss mitigation, erosion control and clearing limits.


Week of 3-5-2012
Trucks will be hauling unclassified from Ingleside to W. Hartley. There will be a considerable amount of Dump trucks coming in and out.
Sewer line replacement at station 31+00 ( approximately) will take place this week.
Survey Staking will be taking place.
Basin #4 of the erosion control will be constructed this week along with armoring the creek bank.
Signs will be place at trails where the bridge work is taking place in addition to safety fence
" Pedestrians and Bicycles Are Not Allowed During Construction"
Heavy equipment will be in use for the duration of the project.

Week of 2/20/2012
The snow this week will hamper efforts to get in on job.
Erosion control will be checked
Week of 2/23/2012
This week we will check our erosion control after all the rain we had this weekend. We will begin our Basins 9,10,11A at station 53:85 so that we may divert the creek in preparation for rerouting sewer line. The work on the walls and drilled piles should be completed this week. A 100 ton crane has been brought in and will be erected to start on the piles for the bridge. On West Hartley at YMCA, storm pipe being installed. Heavy equipment and pipe will be up and down the roadway edges. We may elect to have flaggers at times. PLEASE DRIVE THROUGH CONSTRUCTION ARES WITH CAUTION!!!!!



Week of 2/27/2012
Construction on West Hartley side at Cul-de-sac will be more heavily with trucks coming in and out. A large section of this will be undercut so the End Bent 1 can be installed for the bridge. Sewer pipe will also be replaced with Ductile Iron pipe in order to strengthen this section of outfall where piles will be driven to sustain bridge.
The rain expected this week will be a factor again in our progress.


Week of 2/13/2012
Work this week will include the following;
Construction of skimmer basins
Erosion control fencing
Staking of ponds
Removal of unused soil


Week of 2/6/2012
Heavy work will be concentrated on Ingleside Drive
* PLEASE DRIVE SLOW IN CONSTRUCTION ZONES *
Erosion Control, Work Zone Signs, Heavy Truck Hauling will be underway this week.
Work will also begin on West Hartley Drive at Cul-de-sac. Clearing and erosion control, and some surveying .
Week of 1/30/2012
Weather did not permit work to be done last week, we will begin again this week with the same work load plus;
City of High Point Electric are on West Hartley Drive relocating power poles.
Private Individuals are relocating Lamp Lights and Business signs
Heavy Equipment will be moving in on job site at Ingleside Drive and West Hartley.
Work will begin at cul-de-sac installing construction entrance. Some clearing on Ingleside and a construction entrance installed there as well.
Traffic Control signs and barrels will be put out this week.
Erosion Control measures will continue as clearing and grubbing progress.
The meeting is still scheduled with Army Core of Engineers this Thursday at 10 am on West Hartley Drive.
Week of 1/23/2012
Temporary Safety Fence is up at YMCA
Weather permitting;
Work will begin at cul-de-sac installing construction entrance. Some clearing on Ingleside and a construction entrance installed there as well.
Traffic Control signs and barrels will be put out this week.
Erosion Control measures will continue as clearing and grubbing progress.
Week of 1/16/2012
A meeting will be held at 9:00 am with construction inspector and contractor superintendent to discuss work beginning.
The following work will start;
Installing project traffic signs
Survey control staking
Flagging of control limits
Phase 1 Erosion Control will begin
Week of 1/09/2012
A pre construction meeting was held to discuss job details. There will be another scheduled meeting on 2/02/2012 held on west end at YMCA with contractor and other agencies involved. Some staking by surveyors is being done this week.




Email
Print