Main Street Project

The Main Street Project:


The City of High Point will begin work on a portion of Main Street beginning November 2.  The work will stretch from Parkway Avenue through Westwood Avenue.  We will be upgrading existing aged infrastructure while burying electric and utility lines. The Main Street project will take approximately six months to complete. During this process, the City will shut down this portion of Main Street, however, businesses will remain open and the public will still have access to these locations. While the project is ongoing, however, the flow of traffic will be impacted. We ask motorists to please use the detours provided and be mindful of the safety of work crews in the area.   
MAIN ST
  1. UPDATE 7/8/16
  2. UPDATE 7/25/16
  3. UPDATE 8/5/16
  4. UPDATE 8/15/16
  5. UPDATE 8/29/16
  6. UPDATE 9/28/16

Piedmont Natural Gas has started work on gas lines for the upcoming Main Street project.  Parkway is closed from Main St to Johnson St through next Thursday 7/14. They have two open holes on the North side of Parkway that have to remain open until next week. Next week they will continue with the directional drilling along north Main St. The plan is that they will finish their work on Parkway by next Thursday and then the following Monday they will begin to close Montlieu for continued work.

  1. UPDATE 10/3/16
  2. UPDATE 10/7/16
  3. UPDATE 10/11/16
  4. UPDATE 10/18
  5. UPDATE 10/20
  6. UPDATE 10/27
Change Order - North Main Street Underground Utilities: Council is requested to direct staff on how to move forward with Change Order No. 1 to the Yates Construction Contract for construction of the North Main Underground Utilities Project. Approval of contract will result in the reduction of the Yates Contract in the amount of $246,250.00

Council has approved the Change Order. 
  1. UPDATE 10/31/16
  2. UPDATE 11/2/16
  3. UPDATE 11/4/16
  4. UPDATE 11/10/16
  5. UPDATE 11/18/16
  6. UPDATE 11/24/16
Yates Construction has started to place detour signage around the Main St area where construction will take place.  They have cut the access points to the local business that needed an entrance into their business. They are preparing to close Main St tomorrow morning to begin bringing equipment into the area. 
  1. UPDATE 12/1/2016
  2. Update 12/9/2016

Flow of Traffic


  •  All of the sanitary sewer lines were completed as of yesterday with the exception of the line to the final manhole crossing Parkway Avenue. This will require a special one-to-two-day detour at Farriss Avenue for right turns. All trucks would be required to turn left onto Parkway Avenue. The date for this detour has not been set at this time. 
  •  The HPDOT installed eight additional business wayfinding signs on the traffic barricades at each end of the project.

Construction


  • Crews are approximately 70% complete with laying pavement over the newly placed sanitary sewer lines.
  • Material for the 16" water line will be delivered to the site today, and construction will begin at Westwood Avenue at the end of this week or beginning of next week at the latest.
  • Crews are able to install approximately 100 linear feet per day of the underground duct bank system. After they have completed a vault to vault connection the electric department along with other utilities will begin pulling wires in the completed lines to further expedite the project. 
  • Water trucks continue to be utilized as needed to minimize dust as much as possible. 

Contractor


  • Crews have been working diligently Monday through Saturday each week of the project and have only missed three hours of working time due to weather. 





Why is this project taking place?


The City of High Point is replacing existing infrastructure that dates back to the early 1900's. They will work with various companies like Time Warner Cable, North State Communications, Piedmont Natural Gas, and The City of High Point Electric to replace overhead lines and bury them while the underground water and sewer are being replaced. This will help create a more aesthetically pleasing area that will become a destination for both new and existing business as well as the surrounding community.  

​How long will this project last? 


This project will take approximately six months to complete.  During this time period, the City of High Point will close all lanes of traffic on Main Street from Westwood to Sunset.  We ask that you plan your route according to the detours provided.  

Will I be able to get to the local businesses that run along Main Street? 


The City will maintain access to the business that run along this stretch of the project. Main Street will be shut down through this section, however, the City will provide access to those business who's entrances are only accessible from Main Street.  We will work with each business to create the least amount of impact to each location. Please visit Shop Main Street to see the impacted businesses.  We encourage you to continue the support of the effected businesses during this project. 

Where can I get some information about the Main Street Project? 


If you have any questions about the project, please contact Scott Dingus, Main Street Project Engineer,  at (336) 883-3203 or email scott.dingus@highpointnc.gov or Ryan Ferguson, Marketing Manager, Communications and Public Engagement, at (336) 883-3288 or ryan.ferguson@highpointnc.gov




MAIN STREET DETOURS

MainStDetour1
MainStDetour2