Burton Avenue
This project will improve capacity, safety, drainage, and street aesthetics. Improvements include enhanced transit stops, additional curb and gutter, turn lanes, and sidewalks.
The total project budget is $5,605,259 and is funded by the following sources:
General Obligation bonds $5,000,000
Bond Premium $605,259
$5,605,259
Amount
$5,605,259
Spent/Committed
$46,111
Status
Design is completed by High Point Engineering Department. Electric plans allowing Duke Energy to be on High Point Electric poles have been approved by High Point Electric, with a complete project team review underway. Once the assessment is complete, easement description work will be provided to the High Point Right of Way office to begin easement acquisitions. Construction is scheduled for late FY 2023-24.