The Stadium Streets Project

As the City of High Point prepares for new downtown development, portions of N. Elm Street, Lindsay Street, Pine Street and English Road will closed for infrastructure upgrades.  We will be replacing electric, sewer, water and storm water systems in these roads.  This is part of an overall plan to upgrade  century old infrastructure in our downtown.  

 
Elm Street Detour Map
Elm Street Road closed sign

Update:  1/10/20


This Week 
  • Installed intersection closure of Elm/English
  • Began working on Storm Sewer in the Elm/English intersection
  • Began grading of Appling Way
Next Week
  • Continue working in the Elm/English intersection
  • Continue rough grading/Demo of Appling Way

 

Questions?

Feel free to reach out to Ryan Ferguson or Jeron Hollis with the City of High Point. 

Ryan Ferguson, Marketing Manager
336.883.3288
Ryan.Ferguson@HighPointNC.gov 

Jeron Hollis, Director of Communication and Public Engagement
336.883.8507
Jeron.Hollis@HighPointNC.gov
 
 
Powered by
CivicSend - A product of CivicPlus