The Elm Street Project

As the City of High Point prepares for new downtown development, portions of N. Elm Street between Gatewood Avenue and English Road will be closed beginning Monday, September 10 through March 2019 while underground utility improvements are made. 

 
Traffic Pattern after Nov 12
Elm Street Road closed sign

Update:  3/14/19

Contractors have completed the remaining pipe for the project and finished paving the Church Avenue intersection. They began testing the sewer, and the DOT portion of the project in English Road was completed and paved. Electric crews installed multiple 7x7 vaults in Church Avenue, and have continued to install ductbank in the intersection. Due to the junction of utilities there, there are around 30 conduits in the area. For the remainder of the week and into next week, Garney crews will finish testing the sewer, finish paving and concrete work, and work on moving material out of the lot. Electric will be through the Elm and Church intersection and continue heading towards English Road. The Church intersection will open once traffic signals have been installed. 

 

Questions?

Feel free to reach out to Ryan Ferguson or Jeron Hollis with the City of High Point. 

Ryan Ferguson, Marketing Manager
336.229.3288
Ryan.Ferguson@HighPointNC.gov 

Jeron Hollis, Director of Communication and Public Engagement
336.883.8507
Jeron.Hollis@HighPointNC.gov
 
 
Powered by CivicSend - A product of CivicPlus