As the City of High Point prepares for new downtown development, portions of N. Elm Street, Lindsay Street, Pine Street and English Road will closed for infrastructure upgrades.  We will be replacing electric, sewer, water and storm water systems in these roads.  This is part of an overall plan to upgrade  century old infrastructure in our downtown.  

 
Lindsay Street detour map
Elm Street Road closed sign

Update:  5/1/19

This week, Garney completed the sewer main and services. Next, they'll pave the asphalt, lay the concrete curb and sidewalk and working on cleaning up, seeding and restoration. Lindsay remains closed to through traffic from Ferndale to English, but Ferndale should be reopened by the end of business on Friday, May 3.

 

Questions?

Feel free to reach out to Ryan Ferguson or Jeron Hollis with the City of High Point. 

Ryan Ferguson, Marketing Manager
336.229.3288
Ryan.Ferguson@HighPointNC.gov 

Jeron Hollis, Director of Communication and Public Engagement
336.883.8507
Jeron.Hollis@HighPointNC.gov
 
 
Powered by CivicSend - A product of CivicPlus