As the City of High Point prepares for new downtown development, portions of N. Elm Street, Lindsay Street, Pine Street and English Road will closed for infrastructure upgrades.  We will be replacing electric, sewer, water and storm water systems in these roads.  This is part of an overall plan to upgrade  century old infrastructure in our downtown.  

 
English St. Detour map
Elm Street Road closed sign

Update:  8/15/19

This week crews installed storm sewers and continued to work in the Lindsay/English intersection. They reinstalled waterline on Pine Street and activated the fire hydrant. 

Next week crews will continue to work on the Lindsay/English intersection finishing sewer and beginning the waterline. 


Traffic will remain the same.  Please use caution when taking detours.  



 

Questions?

Feel free to reach out to Ryan Ferguson or Jeron Hollis with the City of High Point. 

Ryan Ferguson, Marketing Manager
336.229.3288
Ryan.Ferguson@HighPointNC.gov 

Jeron Hollis, Director of Communication and Public Engagement
336.883.8507
Jeron.Hollis@HighPointNC.gov
 
 
Powered by
CivicSend - A product of CivicPlus